Internally the underfloor heating
has been laid and covered with screed ready for the floor finish, once dried. Externally the scaffolding has
now been removed to allow for the installation of the eaves, gutters and
downpipes and the external works have commenced starting with the block paving.
Monday, 18 August 2014
Week 12
The timber roof structure was completed
followed by the installation of the natural slate coverings and the external windows
and doors making the building watertight.
The feature Oak Screen is now fitted and
will provide ample natural light into the activity space for the residents.
Week 10
The works are progressing well in relation to the programme with the substructure now complete. The scaffold and masonry
superstructure were built a couple of days ahead of programme allowing for the wall
plate and timber roof trusses to be installed.
The underground drainage installation has been tested and the temporary
hoarding to the existing corridor was placed to allow for the opening up of the
existing walls and roof. A vision panel within the temporary hoarding provides
light into the existing corridor and has been kindly decorated by a local
artist Anne Bennett.